Hingham, MA · Murphy Family Renovation
Budget details are password-protected
Incorrect codeword — try again
| Vendor / Firm | Category | Amount Paid |
|---|---|---|
| Loading vendor data… | ||
| Total | — | |
📷
Progress photos will appear here as the project advances.
Photos are added directly to the project Drive folder.
Major scope and cost decision. Adding a garage changes the footprint, permits, and budget materially. Decision affects framing timeline.
Siding material, color palette, trim, and roofing selections. Needed before exterior work begins.
Denisson has provided a rough estimate (Sept 2025). Final contract scope, fee structure, and schedule need to be agreed before full construction can proceed.
HELOC application is a parallel workstream. Determines available capital and draw schedule for construction payments.
| Date | Decision | Who Decided | Notes |
|---|---|---|---|
| Oct 2025 | Site Plan Approved | Hingham Planning Board | Approved as submitted. No variances required. |
| Jan 2026 | Building Permit Issued | Town of Hingham | Full building permit in hand. Demo and construction may proceed. |
| # | Date | Description | Requested By | Cost Impact | Status |
|---|---|---|---|---|---|
| No change orders yet — this table will populate once the GC contract is active. | |||||